Industry and Infrastructure  307


             requirements. The portal is planned to mature into a central information pool for sourcing of
             capital goods and MRO (maintenance, repair and overhaul) of items of the oil and gas companies
             which in turn is expected to provide clear demand projections to enable the manufacturers to
             enhance  their  capacity  and scope. This portal,  which is accessible  to all  stakeholders  is an
             important step towards AtmaNirbhar Bharat.  The measures taken to enhance theinvestments on
             gas grid are encapsulated in Box 9.

             8.73  The petroleum sector played a critical role throughout the COVID 19 lockdown period
             by maintaining fuel supplies across the country, without any interruption. The scheme of three
             free cylinders to Ujjwala beneficiaries provided much-needed relief to the poor households
             during Covid times. The second phase of the Pradhan Mantri Ujjwala Yojana, Ujjawala 2.0,
             was launched on 10 August, 2021 on pan India basis to provide additional one crore LPG
                                 th
             connections along with free first refill and stove. As on 25.10.2021, while more than 1 crore
             applications have been received in this phase, a total of 54.01 lakh LPG connections have been
             released. Ujjwala 2.0 focuses on migrants and poor women from low LPG coverage areas.


                       Box 9: Measures taken to develop the national gas grid and city
                                             gas distribution network


               National  Gas  Grid:  With  the  aim  to  create  nationwide  gas  grid,  Petroleum  and  Natural  Gas
               Regulatory Board (PNGRB) has authorized approximately 33,764 km natural gas pipeline network
               across the country, as on 31.03.2021. The National Gas Grid would connect all major demand and
               supply centres in India. This would ensure easy availability of natural gas across all regions and
               also potentially help to achieve uniform economic and social progress.  As on 31 March 2021,
               19,998 km of natural gas pipelines are operational and 15,369 km are under various stages of
               construction.
               Pradhan Mantri Urja Ganga (2016): In order to develop the national gas grid, the Government
               has taken a decision to provide a capital grant of Rs.5176 crore (i.e., 40percent of the estimated
               capital cost of Rs.12,940 Cr) for development of a 2655 Km long Jagdishpur-Haldia -Bokaro-
               Dhamra Gas Pipeline (JHBDPL) project. It will pass through 50 districts in the State of Uttar
               Pradesh, Bihar, Jharkhand, Odisha & West Bengal
               North  East  Gas  Grid  (2020):  Government  has  approved  the  North  East  Gas  Grid  project  of
               Indradhanush Gas Grid Limited (IGGL) with Viability Gap Funding (VGF) / Capital Grant at
               60percent (Rs.5,559 crore) of the estimated cost of Rs.9,265 crore. The1,656 km long North East
               Gas Grid will connect eight North-Eastern states.
               City Gas Distribution Network (CGD): PNGRB has authorized 232 geographical areas (GAs)
               for  development  of  CGD  network  across  the  country  covering  more  than  400  districts  in  27
               States/UTs which covers around 71percent of India’s population and 53 percent of area. As on
               31.07.2021, a total of approx. 79.47 lakh PNG Domestic connections and 3323 CNG stations have
               been commissioned in the country.

             Electricity

             8.74  India  has  witnessed  a  significant  transformation  from  being  an  acutely  power  deficit
             country to a situation of demand being fully met. India has also made remarkable strides to